1.Agile teams are preparing to embark on a large-scale story involving some architectural risks. Since the next iteration has been planned, how should agile project managers solve this problem?
- A. Put off the story and keep the team moving
- B. Review the requirements and create a detailed specification
- C. Add the story to the risk register and analyze it with the customer
- D. Carry out inspection work to better understand the risk
敏捷團隊正在準備著手從事一個涉及一些構架風險的大規模故事。由于下一個迭代已經計劃完畢,敏捷項目管理師應該如何解決這個問題?
- A、推遲該故事的工作,保持團隊速度
- B、重新查閱需求,創建詳細的規范
- C、在風險登記冊上添加該故事,并與客戶一起分析
- D、執行考察工作,更好地理解該風險
2.Agile team is committed to product development. What activities can help the team establish good coordination?
- A. Daily station meeting
- B. Issue meeting
- C. To do improvement
- D. Release planning meeting
敏捷團隊正致力于產品開發,哪些活動可以幫助團隊建立良好的協調?
- A、每日站會
- B、發布問題會議
- C、待辦事項改進
- D、發布計劃會議
3.The customer rejected a web application developed by the team because the customer thought the requirements were missing. What steps should the team take to ensure that the development work passes the acceptance?
- A. Perform regular reviews and product demonstrations with customers
- B. Start a new project with new demands from customers
- C. Communicate all changes during product presentation
- D. Get approval from project leader before product demonstration
客戶拒收團隊開發的一個 Web 應用程序,因為客戶認為需求被遺漏。為確保開發的工作通過驗收,團隊應采取什么步驟?
- A、與客戶一起執行定期評審和產品演示
- B、對客戶的新需求重新開始新項目
- C、在產品演示期間溝通所有變更
- D、在產品演示之前獲得項目負責人的批準